OWB: Subproject actuals and ETC are not rolling up to the subproject level in views, but Total Usage does.

Posted @ 02/13/2013  02:43 PM By Federico Pena

Description
OWB: Subproject Actuals and ETC are not rolling up to the subproject level. Add the Task Actual Usage, Task Estimate to Complete and Task Total Usage values to a view. Open a master that has a subproject with Actuals and etc. Apply the view and the Actual Usage and Estimate to complete fields do not display values at the subproject level, but Total Usage does.
Steps to Reproduce:

    1. Create a project with a phase; activity and task (give a task a two week duration).

 

    1. Add a resource to the project and task.

 

    1. Edit ETC to 48 hours if it does not automatically populate.

 

    1. Post 40 hours Actuals to the task.

 

    1. Create a master project.

 

    1. Add the subproject to the master.

 

    1. Open the master in OWB.

 

    1. Edit the Gantt chart to add the following fields: Task Actual Usage, Task Estimate to Complete and Task Total Usage.

 

    View the changed Gantt chart.

Expected Result: To see 40 hours Actuals; 8 hours etc and 48 hours total usage at the subproject level.

Actual Result: You see the values at the task, activity and phase level for Actuals and ETC, but not the subproject level. For Total usage you do see 80 hours at all levels.
Solution
Workaround:
None

Status/Resolution:
Resolved in Clarity 12.1.0
Resolved in Clarity 12.0.6 Generic Patch. Reference TEC522707.
Resolved in Clarity 13.0.0

“Solutions provided by CA Technologies”